Proposal of Production Planning and Control (PPC) guidelines for materials management in a small-scale construction company
DOI:
https://doi.org/10.5281/zenodo.20331239Keywords:
Production Planning and Control, materials management, Last Planner System, construction industryAbstract
Production Planning and Control constitutes a strategic component for coordinating resources, schedules, and materials in the construction industry. In small construction firms, its absence or low level of formalization tends to foster parallel controls, information fragmentation, and reduced managerial reliability. This study aimed to diagnose the limitations of the prevailing materials management model in a small-scale construction company located in Rio de Janeiro and, based on this diagnosis, to propose guidelines for structuring a PPC system. Methodologically, the research is characterized as qualitative and applied, developed through a case study, using document analysis, direct observation, and institutional records. The findings indicated reliance on spreadsheets, partial use of the ERP system, and low integration among planning, procurement, and warehousing functions. In response to the diagnosis, guidelines were proposed and structured around three pillars: adoption of the Last Planner System, improved utilization of the ERP system, and the development of performance indicators. It is concluded that the proposed guidelines may contribute to enhancing process integration and the reliability of information, although their effectiveness depends on future implementation and empirical validation.
Downloads
References
ALNAJJAR, Omar; ATENCIO, Edison; TURMO, Jose. A systematic review of Lean Construction, BIM and emerging technologies integration: identifying key tools. Buildings, v. 15, n. 16, p. 2884, 2025.
ANGELIM, Vanessa Lira; MIRANDA FILHO, Antônio Nunes de; BARROS NETO, José de Paula; HEINECK, Luiz Fernando Mählmann; ALVES, Andreia Cardoso. Medium-term planning considering the roles of the Last Planner System in production strategy and management. Ambiente Construído, Porto Alegre, v. 25, e146585, 2025.
BALLARD, Herman Glenn. The last planner system of production control. 2000. Tese (Doutorado em Engenharia Civil) – University of Birmingham, Birmingham, 2000. Disponível em: <https://etheses.bham.ac.uk/id/eprint/4789/>. Acesso em: 16 mar. 2026.
BAXTER, Pamela; JACK, Susan. Qualitative case study methodology: study design and implementation for novice researchers. The Qualitative Report, [S. l.], v. 13, n. 4, p. 544-559, 2008.
BONESI-DE LUCA, Fabiana Maria; VARGAS, Fabrício Berger de; FORMOSO, Carlos Torres; BULHÕES, Iamara Rossi. Método para implementação do trabalho padronizado como elemento adicional do planejamento e controle baseado em localização. Ambiente Construído, Porto Alegre, v. 24, 2024.
DING, Fan; LIU, Min; HSIANG, Simon M.; HU, Peng; ZHANG, Yuxiang; JIANG, Kewang. Duration and labor resource optimization for construction projects—A Conditional-Value-at-Risk-Based analysis. Buildings, v. 14, n. 2, p. 553, 2024.
GALAGALI, Anagha Anirudh; SANDBHOR, Sayali; RUIKAR, Kirti. A survey on enterprise resource planning and building information modeling integration: a Construction 4.0 perspective. Buildings, v. 14, n. 10, p. 3165, 2024.
GAO, Shang; CHAN, Toong-Khuan; HENDY, Phil. Adoption of the digitalised last planner system in infrastructure projects: an Australian case study. Construction Innovation, v. 25, n. 3, p. 994–1013, 2025.
GARCÉS, Gonzalo; FORCAEL, Eric; OSORIO, Cristian; CASTAÑEDA, Karen; SÁNCHEZ, Omar. Systematic review of Lean Construction: an approach to sustainability and efficiency in construction management. Journal of Infrastructure Preservation and Resilience, v. 6, art. 6, 2025.
GÖRSCH, Christopher; SEPPÄNEN, Olli; PELTOKORPI, Antti; LAVIKKA, Rita. Task planning and control in construction: revealing workers as early and late planners. Construction Management and Economics, v. 42, n. 5, p. 431-450, 2024.
HE, Chuanni; LIU, Min; HE, Weilin; WANG, Zijian; HSIANG, Simon. Addressing the information silo of construction planning constraints: a graph retrieval augmented generation approach. Engineering, Construction and Architectural Management, 2025.
KARAZ, Mahmoud; TEIXEIRA, José Manuel Cardoso; AMARAL, Tatiana Gondim do. Mitigating making-do practices using the Last Planner System and BIM: a system dynamic analysis. Buildings, v. 14, n. 8, p. 2314, 2024.
LAFHAJ, Zoubeir; REBAI, Slim; ALBALKHY, Wassim; HAMDI, Olfa; MOSSMAN, Alan; DA COSTA, Angela Alves. Complexity in construction projects: a literature review. Buildings, v. 14, n. 3, p. 680, 2024.
LEÓN-ROMERO, Luvis P.; AGUILAR-FERNÁNDEZ, Mario; LUQUE-SENDRA, Amalia; ZAMORA-POLO, Francisco; FRANCISCO-MÁRQUEZ, Misaela. Characterization of the information system integrated to the construction project management systems. Heliyon, v. 10, n. 11, e31886, 2024.
LEÓN, William; GUEVARA, Jose; GARCIA-LOPEZ, Nelly P. Impact of time-based variability on planning reliability in construction projects: analysis of production management systems. Engineering, Construction and Architectural Management, 2025.
LIMA, Mahara Iasmine Sampaio Cardoso; COSTA, Dayana Bastos. Recomendações e boas práticas para a integração do monitoramento da segurança com drone ao planejamento e controle da segurança de obras. Ambiente Construído, Porto Alegre, v. 23, n. 1, p. 213-231, jan./mar. 2023.
LINCOLN, Yvonna S.; GUBA, Egon G. Naturalistic inquiry. Beverly Hills: Sage, 1985.
MACIEL DE ABREU, João Paulo; DE CAMARGO CARDOSO, Gabriel; FERNANDES MARCHIORI, Fernanda; GOMES DE OLIVEIRA BRANDSTETTER, Maria Carolina; MÄHLMANN HEINECK, Luiz Fernando. Mão-de-obra polivalente: uma discussão desse elo perdido da lean construction em empresas brasileiras. Ambiente Construído, Porto Alegre, v. 23, n. 4, p. 7-23, 2023.
MILES, Matthew B.; HUBERMAN, A. Michael. Qualitative data analysis: an expanded sourcebook. 2. ed. Thousand Oaks: Sage, 1994.
MOREIRA, Álvaro Alexandrino Silva; AVANCINI, Paulo Roberto; SOUSA, Erivelto Fioresi de. Implementing the Last Planner System on a construction project. RINTERPAP - Revista Interdisciplinar de Pesquisas Aplicadas, v. 1, n. 1, 2024.
PATTON, Michael. Qualitative evaluation and research methods. 2. ed. Newbury Park: Sage, 1990.
POWER, William; SINNOTT, Derek; LYNCH, Patrick. Synthesizing Last Planner® System, Takt, and Scrum Theory and Practice to Enhance Construction Project Delivery. Lean Construction Journal, 2024, p. 16-28.
PRABAHARAN, Ragavi; SUNDARALINGAM, Karthikeyan; TAMILNATHAN; MOHANBABU. Assessment of Last Planner® System Maturity and Engagement of Participants by Linguistic Action Perspective Approach—A Case Study. In: Sustainable Lean Construction. Singapore: Springer, 2023. p. 165-174.
RAITVIIR, Christopher-Robin; LILL, Irene. Conceptual framework of information flow synchronization throughout the building lifecycle. Buildings, v. 14, n. 7, 2207, 2024.
SHEIKHKHOSHKAR, Moslem; BRIL EL-HAOUZI, Hind; AUBRY, Alexis; HAMZEH, Farook; SAKIKHALES, Mohammad. An innovative integrated framework for multi-level production planning and control systems in construction. Developments in the Built Environment, v. 19, p. 100524, 2024.
SHEIKHKHOSHKAR, Moslem; BRIL EL-HAOUZI, Hind; AUBRY, Alexis; HAMZEH, Farook; RAHIMIAN, Farzad. From process-based to technology-driven: a study on functionalities as key elements of collaborative planning methods for construction projects. Production Planning & Control, 2024a.
SILVEIRA, Bruno Falcón; COSTA, Dayana Bastos. Method for automating the processes of generating and using 4D BIM models integrated with location-based planning and Last Planner® System. Construction Innovation, v. 24, n. 4, p. 1005–1025, 2024.
STAKE, Robert E. The art of case study research. Thousand Oaks: Sage, 1995.
TARESH, Noor Shaheed Sachit; GOLESTANIZADEH, Mahboobeh; SARVARI, Hadi; EDWARDS, David J. The impact of using information systems on project management success through the mediator variable of project risk management: results from construction companies. Buildings, v. 15, n. 8, 1260, 2025.
TRIANA GONZÁLEZ, Samuel Jesús; LOZANO DÍEZ, Rafael Vicente. Systematization of BIM data management to improve centralization, interoperability and traceability of building asset information in digital environments. International Journal of Architectural Computing, 2024.
YANG, Huixing; WANG, Deling. Application of Lean–Agile hybrid methods in complex construction project management. Buildings, v. 15, n. 13, p. 2349, 2025.
YIN, Robert K. Case study research: design and methods. 3. ed. Thousand Oaks: Sage, 2003.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Gustavo Dourado Silva, Renato Sepulveda Barino, Claudia Brito da Cunha, Raphael Barino

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Copyright Policy
By submitting a manuscript for publication in the journal Advances in Global Innovation & Technology (@_GIT), authors agree, in advance and unrestrictedly, to the following terms:
- The authors retain the copyright and grant to the Journal Advances in Global Innovation & Technology (@_GIT) the right of first publication of the manuscript, without any financial burden, and waive any other remuneration for its publication in the Journal of Advances in Global Innovation & Technology (@_GIT).
- Upon submission to the Journal of Advances in Global Innovation & Technology (@_GIT), the manuscript is automatically licensed under the Creative Commons Attribution License, which allows the sharing of the work with acknowledgment of authorship and initial publication in the Journal Advances in Global Innovation & Technology (@_GIT).
- Authors are authorized to enter into additional contracts separately, for non-exclusive distribution of the version of the work published in the Journal Advances in Global Innovation & Technology (@_GIT) (publish in repositories or as a book chapter), with acknowledgment of the initial publication in the Journal Advances in Global Innovation & Technology (@_GIT), provided that such agreement does not imply an endorsement of the content of the manuscript or the new vehicle by the Journal of Advances in Global Innovation & Technology (@_GIT).
- Authors are allowed and encouraged to publish and distribute their work online, in institutional repositories, for example after the editorial process is completed.
- The authors warrant that they have obtained proper permission from their employers for the transfer of rights under this agreement, if those employers own any copyright in the manuscript. In addition, the authors assume any and all responsibility for possible copyright infringements of these employers, exempting Advances in Global Innovation & Technology (@_GIT) from any and all liability in this regard.
- The authors assume all responsibility for the content of the work, including the due and necessary authorizations for the disclosure of data collected and results obtained, exempting the Journal of Advances in Global Innovation & Technology (@_GIT) from any and all liability in this regard.